Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

Yes. Fishing and hunting are regulated under state laws. Where hunting and fishing were allowed prior to designation, they may continue. The river-administering Secretary may, however, designate no hunting zones or periods in which no hunting is allowed for public safety or other reasons. The Secretary must issue such regulation in consultation with the wildlife agency of the state(s).

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under various laws and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

A river authorized for study under Section 5(a) of the Wild & Scenic Rivers Act is subject to the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Act.

The river is protected for the duration of the study plus up to three years after the required report is submitted (along with the President’s recommendation) to Congress. Should Congress not act within the three-year time frame, the river is no longer afforded protection by the Wild & Scenic Rivers Act. In cases where a study has not been submitted to Congress, the statutory protections...

Rivers designated under Section 3(a) of the Wild & Scenic Rivers Act, and most designated under Section 2(a)(ii), are classified in one of three categories depending on the extent of development and accessibility along each section. Designated river segments are classified and administered under one of the following, as defined in Section 2(b) of the Wild & Scenic Rivers Act:

...

The need to amend a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed amendment associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP) as a basis to make a recommendation to Congress to amend the Wild & Scenic Rivers Act.

The river-administering agency can only recommend such a change to Congress. A subsequent...

Yes, the federal government may seek to control use on adjacent lands under very limited circumstances. The Constitution gives the federal government certain limited powers to control uses on state-owned lands that affect adjacent federal property. These powers may be exercised through the Property Clause, which provides that, “Congress shall have the power to make all needful rules and regulations respecting the territory or the property belonging to the United States.”

The federal government may also regulate use and/or activities occurring on the surface waters...

The federal wild and scenic river-administering agency is responsible for implementing the Wild & Scenic Rivers Act’s requirements, including the development of a comprehensive management plan for each river within three full fiscal years from the date of designation. It is also responsible to protect and enhance a river’s values, through its authorities on federal lands and through voluntary, cooperative strategies developed with other governments, tribal nations, and landowners on non-federal lands, and to evaluate water resources projects under Section 7(a).

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

Timber management activities on federal lands within wild and scenic river corridors must be designed to help achieve land-management objectives consistent with the protection and enhancement of the values that caused the river to be added to the National Wild & Scenic Rivers System. Management direction needed to protect and enhance the river’s values is developed through the river planning process. Wild and scenic river designation is not likely to significantly affect timber management activities beyond existing measures to protect riparian zones, wetlands, and other resource values...

The federal government has rarely exercised its eminent domain powers with respect to wild and scenic rivers. Of the 226 rivers in the National Wild & Scenic Rivers System as of June 2022, condemnation for fee title has been used on only four rivers. Nearly all of the federal government’s use of condemnation occurred in the early years of the Wild & Scenic Rivers Act’s implementation when the attitudinal climate was one of federal acquisition. Similarly, the use of scenic easement condemnation has also been used very rarely, and then only on seven rivers, all designated prior to...

There are two ways rivers are designated in the National Wild & Scenic Rivers System:

  • By Act of Congress
    This requires legislation to amend Section 3(a) of the Act.  Rivers designated by Congress are listed in Section 3(a) of the Act.
  • By the Secretary of the Interior
    This...

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

To be eligible for designation, a river must be free-flowing and contain at least one "outstandingly remarkable value," i.e., scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar value.

Wild and scenic river study reports are prepared in three instances:

  1. When Congress authorizes a study pursuant to Section 5(a) of the Wild & Scenic Rivers Act.

  2. For eligible rivers that have also been determined suitable by a federal land management agency pursuant to Section 5(d)(1) of the Wild & Scenic Rivers Act, when the agency deems it appropriate to forward the recommendation.

  3. For state-nominated Section 2(a)(ii) rivers, the National Park Service prepares a report determining whether the candidate river meets the requirements of...

No. The designation does not supersede existing, valid water rights.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

When Congress proposes a bill to designate an eligible river for which a suitability study has not been completed, the potential river-administering agency should endeavor to:

  1. Describe the resource and social factors typically evaluated in a study;
  2. Identify potential issues; and
  3. Assess its ability to manage the recommended component as a wild and scenic river.

This information provides the basis for the Administration’s decision to support or oppose the proposed designation.

Agency officials are required to coordinate when their responsibilities relevant to wild and scenic rivers overlap.  Officials should determine the level of study to be conducted, who will lead the study, and, to the extent necessary and feasible, prepare a joint document for submission to Congress or congressional delegations.

No. Non-indigenous species need not be removed unless they are degrading other important resource values. Practical considerations, such as the effort or expense of eradicating a non-indigenous species and its importance (e.g., game species), should also be considered. This issue is generally addressed in the management plan.

Differences include, but are not limited to, the following areas:

  1. Motorized boats and other motors may be allowed in wild and scenic rivers classified as wild, whereas the administering Secretary has the discretion to continue the use of motorized boats and airplane landings in wilderness where such uses are traditionally established. In areas that are both a wild and scenic river and wilderness, the most restrictive provisions of the two acts apply, subject to any area-specific legislative language.

  2. New dams are prohibited in wild and scenic rivers. The...

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

No. Lands owned by a state may be acquired only by donation or exchange per Section 6(a)(1) of the Wild & Scenic Rivers Act.

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

Yes, a federal reserved water right is generally adjudicated in state court (e.g., basin-wide adjudication) in the western United States. It is less clear how federal reserved water rights are adjudicated in the eastern United States. Contact a staff expert and/or legal counsel when trying to protect water quantity.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel....

Ideally one coordinated CRMP is developed with each wild and scenic river-administering agency documenting its respective decisions. In a few cases, separate plans may be required. However, even in this case, the planning process is conducted jointly to the greatest extent possible to ensure consistency of outstandingly remarkable values, classification, standards, and monitoring.

A Section 5(d)(1) study river is protected to the extent of each study agency’s authority and not by the Wild & Scenic Rivers Act. Each agency’s policy is to protect eligible rivers and rivers determined suitable for designation for the life of the respective agency land use plan. A river determined not suitable for designation need no longer be protected as a potential addition to the National Wild & Scenic Rivers System once the study, with its related decision document, is completed.

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

For 5(a) studies, the study report, planning document and combined National Environmental Policy Act (NEPA) analysis are submitted to the agency head for review and subsequent transmittal to Congress, which decides the final disposition of the river.

For 5(d)(1) studies, the study report and combined NEPA analysis (if conducted as a separate study), or study report prepared from the underlying land management plan, are submitted through the study agency and its respective department for review. The final study report is transmitted by the appropriate Secretary to Congress, which...

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

Land acquisition is one tool for protecting and enhancing river values. It may also be an important means of providing public access to a wild and scenic river. Notwithstanding Section 6 of the Wild & Scenic Rivers Act, however, Congress has pre-empted some or all of the Wild & Scenic Rivers Act’s federal land acquisition authorities in the enabling acts for certain wild and scenic rivers where the river study demonstrated that protective zoning or other conservation practices provided adequate safeguards for river values.

No. The Wild & Scenic Rivers Act specifically prohibits the federal government from expending funds on Section 2(a)(ii) rivers, except to manage federal lands or to provide technical assistance to local managers.

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Projects with the following attributes are generally considered most harmonious with river ecosystems:

  • Those made of native materials, e.g., wood, rock, vegetation, and so forth that are similar in type, composition or species to those in the vicinity of the project.
  • Those using construction materials that are natural in appearance, e.g., logs with bark intact as opposed to being peeled and whole naturally weathered rocks as opposed to split or fractured (i.e., riprap).
  • Those with materials placed in locations, positions, and quantities mimicking natural...

Generally, no. Any provisions for public use of private lands must be specifically included in the terms of the easement. Depending upon the terms and conditions of each easement, public access rights may or may not be involved. For example, a scenic easement may only involve the protection of narrowly defined visual qualities with no provisions for public use. A trail or road easement by necessity may involve public use provisions.

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

The priority date is the date the river was added to the National Wild & Scenic Rivers System.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Due to the dams, diversions, and water resource development projects that occurred from the 1930’s to the 1960’s, the need for a national system of river protection was recognized by conservationists (notably Frank and John Craighead), congressional representatives (such as Frank Church and John Saylor), and federal agencies.  The Act was an outgrowth of the national conservation agenda of the 1950’s and 1960’s, captured in the 1962 recommendations of the Outdoor Recreation Resources Review Commission.  The Act concluded that selected rivers be preserved in a free-flowing...