No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Benefits may include, but are not limited to, providing managers tools or mechanisms to protect free-flowing condition, i.e., protection of river values through the assessment of hydroelectric facilities or water resource development projects within the designated reach; protection and enhancement of water quality and outstandingly remarkable values; and, if a river’s management plan objective, promotion of economic development, tourism, or recreational use. Based on current limited studies, indications are that property values remain stable or increase on designated rivers. This is often...

The government typically provides technical assistance to find ways to alleviate or mitigate the actual or potential threat(s). Purchasing a partial right (easement) or the property in fee title is usually the last resort. If an easement is purchased, the owner would sell certain development rights and receive a payment, yet retain title to the land.

The priority date is the date the river was added to the National Wild & Scenic Rivers System.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

River-administering agencies use a variety of approaches to protect or enhance water quality including, but not limited to: developing a cooperative water quality plan with the EPA and state agencies; securing cooperative funding to assess or remediate problems; and providing technical assistance to landowners and communities, often through local conservation districts.

Local government entities are encouraged by federal wild and scenic river-administering agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures. Their participation in development of the comprehensive river management plan (CRMP) in areas of mixed ownership is essential to ensure an enduring planning strategy that protects river values and respects the rights of landowners. In some cases, local governments have chosen to strengthen land-use requirements during a wild and scenic river study, in...

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

Subject to valid existing rights, rivers authorized for study under Section 5(a) of the Wild & Scenic Rivers Act are withdrawn under the mining laws while in study status; this withdrawal covers the bed and bank and federal lands situated within one-quarter mile of the bank on each side of the river. River study areas are not withdrawn from mineral leasing but are subject to conditions determined by the appropriate Secretary necessary to safeguard the area during the study period. However, the bed and bank and federal lands within two miles of the bank of each side of the rivers...

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

Yes, a CRMP is developed in compliance with the NEPA. The purpose and need for the proposed action is to protect and enhance the values for which the river was designated (free-flowing condition, water quality, and outstandingly remarkable values), within its classification(s). The proposed action establishes appropriate goals, objectives, and/or desired conditions to meet those purposes. Alternative courses of actions are developed and analyzed relative to achieving overall goals and desired conditions within the wild and scenic river corridor. A “no action” alternative, representing the...

Yes.  There are three classifications (wild, scenic and recreational) that may be applied to a particular river segment. Distinct segments along the designated reach may contain differing and non-overlapping classifications (wild, scenic, or recreational), e.g., a 100-mile wild and scenic river may be classified as wild for 50 miles, scenic for 30 miles, and recreational for 20 miles.

Rivers designated under Section 3(a) of the Wild & Scenic Rivers Act, and most designated under Section 2(a)(ii), are classified in one of three categories depending on the extent of development and accessibility along each section. Designated river segments are classified and administered under one of the following, as defined in Section 2(b) of the Wild & Scenic Rivers Act:

...

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

River-administering agencies must evaluate proposed water resources projects under the appropriate standard of Section 7. The evaluative standard for projects located within a wild and scenic river corridor, Section 5(a) study area, or qualifying Section 2(a)(ii) application area is whether the project would have a “direct and adverse effect.” The evaluative standard for projects located downstream, upstream, or on a tributary to a wild and scenic river corridor or Section 5(a) study area is whether the project would “invade the area or unreasonably diminish” for designated wild and scenic...

Section 16(b) of the Wild & Scenic Rivers Act, defines a “river” as “a flowing body of water . . . or portion, section, or tributary thereof. . . .”  “Free-flowing” is defined as “existing or flowing in natural condition without impoundment. . . .”  Therefore, any section of river with flowing water meets the technical definition of free flowing, even if impounded upstream.

There are two ways rivers are designated in the National Wild & Scenic Rivers System:

  • By Act of Congress
    This requires legislation to amend Section 3(a) of the Act.  Rivers designated by Congress are listed in Section 3(a) of the Act.
  • By the Secretary of the Interior
    This...

Corridor boundaries are established to protect the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated. Generally, the corridor width for designated rivers cannot exceed an average of 320 acres per mile which, if applied uniformly along the entire designated segment, is one-quarter of a mile (1,320 feet) on each side of the river. Boundaries may be wider or narrower, but are not to exceed the 320 acre average per mile per Section 3(b) of the Wild & Scenic Rivers Act without approval by Congress. The acreage of any islands...

Wild and scenic river designations generally cause property values to remain stable or increase. For example, see Economic Benefits of Conserved Rivers: An Annotated Bibliography (Porter, B., Collier, S., Becerra, N., and Schultz, J. 2001. National Park Service – Rivers and Trails Conservation and Assistance Program, Washington, DC. 27pp.).

Yes. To withdraw a scenic or recreational river segment, the managing agency must submit a separate public land order or notice of realty action.

The following summarizes the sections of the Wild & Scenic Rivers Act related to water resources (quality and quantity):

Section 1(b) of the Wild & Scenic Rivers Act establishes that the national policy of dam and other construction be complemented by a policy that would preserve other selected rivers or sections thereof “in their free-flowing condition to protect the water quality of such rivers and to fulfill other vital national conservation purposes.”

Section 10(a) states: “Each component of the national wild and scenic rivers system shall be administered in...

No. Lands owned by a state may be acquired only by donation or exchange per Section 6(a)(1) of the Wild & Scenic Rivers Act.

Landowners can charge a fee for crossing private lands to fish, except where a public access easement exists. The designation of a wild and scenic river does not change landowner rights unless all, or a portion of those use rights, are acquired from the landowner.

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

A river authorized for study under Section 5(a) of the Wild & Scenic Rivers Act is subject to the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Act.

The river is protected for the duration of the study plus up to three years after the required report is submitted (along with the President’s recommendation) to Congress. Should Congress not act within the three-year time frame, the river is no longer afforded protection by the Wild & Scenic Rivers Act. In cases where a study has not been submitted to Congress, the statutory protections...

No. Navigability determinations are based on factors other than wild and scenic river designation. Because of this, designation does not affect ownership of the submerged lands [or minerals lying] under the river.

Local government entities are encouraged by federal management agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures.

State land-use requirements often require each local jurisdiction to address uses and activities within wild and scenic river areas in their planning updates. Such local planning may be carried out by comprehensive plan policies, zoning requirements, negotiations with landowners, or through other mechanisms.

When Congress proposes a bill to designate an eligible river for which a suitability study has not been completed, the potential river-administering agency should endeavor to:

  1. Describe the resource and social factors typically evaluated in a study;
  2. Identify potential issues; and
  3. Assess its ability to manage the recommended component as a wild and scenic river.

This information provides the basis for the Administration’s decision to support or oppose the proposed designation.

Circumstances where agencies should always seek information and advice from each other are:

  1. In agency inventory and planning processes, and environmental analysis processes for aquatic ecosystems and regional watersheds; and,
  2. When proposed actions have the potential of affecting other agency-administered portions of the river.

In the Wild & Scenic Rivers Act, river values identified include scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values. The Wild & Scenic Rivers Act does not further define outstandingly remarkable values. However, agency resource professionals have developed interpretive criteria for evaluating river values (unique, rare, or exemplary) based on professional judgment on a regional, physiographic, or geographic comparative basis. (Refer to The Wild & Scenic River Study Process (1999).)

No. The United States determines the quantity necessary to protect flow-dependent outstandingly remarkable values.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Yes.  For purposes of eligibility evaluation, the volume of flow is sufficient if it is enough to sustain or complement the outstandingly remarkable values identified within the segment.  Rivers with intermittent or non-perennial flows exist within the National Wild & Scenic Rivers System and may be representative of rivers within particular physiographic regions.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

There are a number of steps that federal agencies use in their evaluation process:

  • Assessment of free-flowing condition and resource values.
  • Finding of eligibility or ineligibility.
  • Inventoried or tentative classification based on the development of shoreline, watercourse, and access.
  • Establishment of tentative, preliminary, or proposed boundaries and/or river areas.
  • Establishment of protective management requirements for eligible rivers.

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Section 16(b) of the Act defines free-flowing as “existing or flowing in a natural condition without impoundment, diversion, straightening, rip-rapping, or other modification of the waterway. The existence, however, of low dams, diversion works and other minor structures at the time any river is proposed for inclusion in the national wild and scenic rivers system shall not automatically bar its consideration for such inclusion: Provided, that this shall not be construed to authorize, intend, or encourage future construction of such structures in components of the national wild and...

Timber management activities on non-federal lands within wild and scenic river corridors are guided by state and local authorities. Under the Wild & Scenic Rivers Act, the only way the federal government can restrict private timber management is through purchase of timber rights (in easement or fee title). The river manager may provide technical assistance and/or work with state/local governments to protect river values.