The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

Ideally one coordinated CRMP is developed with each wild and scenic river-administering agency documenting its respective decisions. In a few cases, separate plans may be required. However, even in this case, the planning process is conducted jointly to the greatest extent possible to ensure consistency of outstandingly remarkable values, classification, standards, and monitoring.

Protective management of federal lands in the river area begins at the time the river segment(s) has been found eligible.  The free-flowing condition, identified outstandingly remarkable values, and classification are protected to the extent authorized under law and subject to valid existing rights.  Affording adequate protection requires sound resource management decisions based on National Environmental Policy Act (NEPA) analysis.  Protective management should be initiated by the administering agency as soon as eligibility is determined.  Specific management...

Benefits may include, but are not limited to, providing managers tools or mechanisms to protect free-flowing condition, i.e., protection of river values through the assessment of hydroelectric facilities or water resource development projects within the designated reach; protection and enhancement of water quality and outstandingly remarkable values; and, if a river’s management plan objective, promotion of economic development, tourism, or recreational use. Based on current limited studies, indications are that property values remain stable or increase on designated rivers. This is often...

Yes. Legal descriptions along with a map are submitted to Congress in accordance with Sections 3(b) and (c) of the Wild & Scenic Rivers Act and are retained by the administering agency. Requests for maps should be made to the agency field offices which administer the specific study or designated river(s).

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

Federal lands within the boundaries of designated river areas (one-quarter mile—one-half mile for rivers in Alaska located outside national parks—from the bank on each side of the river) classified as wild are withdrawn from appropriation under the mining and mineral leasing laws by Sections 9(a) and 15(2) of the Wild & Scenic Rivers Act. Federal lands within the boundaries of designated river areas classified as scenic or recreational are not withdrawn under the Wild & Scenic Rivers Act from the mining and mineral leasing laws....

Local government entities are encouraged by federal management agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures.

State land-use requirements often require each local jurisdiction to address uses and activities within wild and scenic river areas in their planning updates. Such local planning may be carried out by comprehensive plan policies, zoning requirements, negotiations with landowners, or through other mechanisms.

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

Land acquisition is one tool for protecting and enhancing river values. It may also be an important means of providing public access to a wild and scenic river. Notwithstanding Section 6 of the Wild & Scenic Rivers Act, however, Congress has pre-empted some or all of the Wild & Scenic Rivers Act’s federal land acquisition authorities in the enabling acts for certain wild and scenic rivers where the river study demonstrated that protective zoning or other conservation practices provided adequate safeguards for river values.

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

No. The river study, enabling legislation, and subsequent management planning process will consider how best to protect river values while recognizing private property rights.

No. The Wild & Scenic Rivers Act specifically prohibits the federal government from expending funds on Section 2(a)(ii) rivers, except to manage federal lands or to provide technical assistance to local managers.

In agency parlance used for planning purposes, river “areas” include the entire length of a study or designated river and its adjacent lands, an average of 320 acres per river mile (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). A river “segment” is a portion of the river area which has been delineated for evaluation and planning purposes. Its subsequent classification is dependent upon the level of development of the shoreline, watercourse and access at the time of designation. Significantly different...

Circumstances where agencies should always seek information and advice from each other are:

  1. In agency inventory and planning processes, and environmental analysis processes for aquatic ecosystems and regional watersheds; and,
  2. When proposed actions have the potential of affecting other agency-administered portions of the river.

Rivers included in the National Wild & Scenic Rivers System by act of Congress (under Section 3(a) of the Wild & Scenic Rivers Act) are administered by one of four federal agencies: Bureau of Land Management (BLM), National Park Service (NPS), U.S. Forest Service (USFS), and/or U.S. Fish & Wildlife Service (FWS) as specified in the legislation. Rivers included in the National Wild & Scenic Rivers System at the request of a governor and designated by the Secretary of the Interior (under Section 2(a)(ii) of the Wild & Scenic Rivers Act) are administered by the respective...

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...

Should the purchase of land become necessary, condemnation is typically a last resort and only used when:

  1. Land is clearly needed to protect resource values, or provide necessary access for public recreational use, and a purchase price cannot be agreed upon.

  2. Clear title to a property is needed, in which case condemnation is merely a legal procedure that has nothing to do with government/landowner differences.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

Prior to 1986, Section 3(b) of the Wild & Scenic Rivers Act required the river-administering agency to “prepare a plan for necessary developments in connection with its administration in accordance with such classification.” Through a generic amendment of the Wild & Scenic Rivers Act in 1986, Section 3 was amended with a new subsection requiring a “comprehensive management plan . . . to provide for protection of the river values” (Section 3(d)(1)). The comprehensive river management plan (CRMP) must address:

  1. Resource protection;

  2. Development of lands...

Yes. In some river study authorizations Congress has required the study agency to work with state and local governments and the public to develop a CRMP in concert with the study process to assist in determination of the river’s suitability. Such pre-designation CRMPs have, in some cases, been adopted in the legislation adding the river to the National Wild & Scenic Rivers System. In cases where Congress has not authorized a pre-designation CRMP, agencies have taken the initiative to develop elements of the CRMP in the study report (pre-designation).

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Upon congressional authorization for a study (Section 5(a)) or by federal agency initiative (Section 5(d)(1)).

Administering agencies do not have any authority to control public use of private lands. Granting of access remains the owner’s responsibility and trespass is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

Yes.  The Nationwide Rivers Inventory lists potentially eligible rivers.  Federal agencies should make an eligibility determination for rivers on the Nationwide Rivers Inventory.

Designation may cause an increase in use along the river as new visitors seek it out. However, the wild and scenic river management requirements should ensure that any such increase will not damage resources on private property. If anything, there will be increased oversight after designation, discouraging littering, trespass and vandalism. Private landowners may continue to post their property with “No Trespassing” signs or require users to obtain landowner permission.

Yes it may. Once water rights are adjudicated, the federal reserved water right may affect future water development projects, depending upon the impacts of the new proposal on the river’s flow-dependent values. Adjudications have been completed or are in process on 15 designated wild and scenic rivers. To date, existing flows have been sufficient to protect current and future demands and to meet the purposes for which the river was designated. River-administering agencies can work with local and state agencies to negotiate solutions that accommodate future water needs and that protect wild...

No. Non-indigenous species need not be removed unless they are degrading other important resource values. Practical considerations, such as the effort or expense of eradicating a non-indigenous species and its importance (e.g., game species), should also be considered. This issue is generally addressed in the management plan.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

A variety of methodologies are used to determine instream flows necessary to protect flow-dependent outstandingly remarkable values for a specific wild and scenic river. Methodologies can range from staff/expert opinions (e.g., flows necessary for boating) to complicated hydraulic models (e.g., Instream Flow Incremental Methodology and Physical Habitat Simulation Models) used to simulate fish habitat requirements.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager...

For state-designated rivers, a governor may submit an application to the Secretary of the Interior under Section 2(a)(ii) of the Act.  If found eligible, and if sufficient protection is afforded by the state, the Secretary may make the designation.  Rivers designated in this manner continue to be administered by the state (sometimes with assistance from local governments), except for any federal lands along the river.  If there are federal lands located along the river, the state and federal river-administering agencies may enter into an agreement to outline federal/state...

Projects with the following attributes are generally considered most harmonious with river ecosystems:

  • Those made of native materials, e.g., wood, rock, vegetation, and so forth that are similar in type, composition or species to those in the vicinity of the project.
  • Those using construction materials that are natural in appearance, e.g., logs with bark intact as opposed to being peeled and whole naturally weathered rocks as opposed to split or fractured (i.e., riprap).
  • Those with materials placed in locations, positions, and quantities mimicking natural...

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

Landowners can charge a fee for crossing private lands to fish, except where a public access easement exists. The designation of a wild and scenic river does not change landowner rights unless all, or a portion of those use rights, are acquired from the landowner.

Yes. Congress has frequently added wild and scenic river status to rivers flowing through national parks, national wildlife refuges, and designated wilderness. Each designation recognizes distinct values for protection, and management objectives generally designed to not conflict. In some cases, wild and scenic river designations extend beyond the boundaries of other administrative or congressional area designations, thereby providing additional protection to the free-flowing condition and river values of the area. Section 10(b) of the Wild & Scenic Rivers Act addresses potential...

Generally, existing agricultural and grazing practices, and related structures are not affected by designation. The Wild & Scenic Rivers Act does not give federal agencies authority to regulate private land. Consequently, the only effect of designation is to authorize the purchase of easements within the river corridor, and to enable federal agency staff to provide technical assistance to private landowners interested in reducing impacts on the river’s water quality and riparian integrity.

The Interagency Guidelines interpret Section 10(a) of Wild & Scenic Rivers Act (the protect and enhance mandate) as “a non-degradation and enhancement policy for all designated river areas, regardless of classification. . . . Specific management strategies will vary according to classification but will always be designed to protect and enhance the values of the river area.” The overarching goal articulated in Section 10(a) is to protect existing high-quality conditions while improving conditions when unacceptable impacts are documented, thus leaving each river to future generations in...

Yes. Fishing and hunting are regulated under state laws. Where hunting and fishing were allowed prior to designation, they may continue. The river-administering Secretary may, however, designate no hunting zones or periods in which no hunting is allowed for public safety or other reasons. The Secretary must issue such regulation in consultation with the wildlife agency of the state(s).

Subject to valid existing rights, rivers authorized for study under Section 5(a) of the Wild & Scenic Rivers Act are withdrawn under the mining laws while in study status; this withdrawal covers the bed and bank and federal lands situated within one-quarter mile of the bank on each side of the river. River study areas are not withdrawn from mineral leasing but are subject to conditions determined by the appropriate Secretary necessary to safeguard the area during the study period. However, the bed and bank and federal lands within two miles of the bank of each side of the rivers...

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

Yes. Water may be secured through a variety of protection strategies, in the interim. Ultimately, the United States should secure a federal reserved water right in state court or the appropriate forum. Interim measures may include, but are not limited to: state instream flow programs, reservoir operation schedules, endangered species flow recommendations, conservation techniques, cooperative agreements, and water right purchases from willing sellers.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water...

Most current uses and activities on rivers and adjoining federal lands may continue. Of primary consideration in any river or land-use limitation is the protection and enhancement of the free-flowing condition, water quality, and outstandingly remarkable value(s) that resulted in the river’s designation. Those uses that clearly threaten these values will be addressed in the planning process, or through site-specific environmental analyses on a case-by-case basis where federal lands are involved.

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Corridors may not exceed an average of 320 acres per river mile over the designated portion of the river (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). Agencies delineate boundaries based on natural or manmade features (canyon rims, roads and ridge tops, etc.) and legally identifiable property lines.

Prior to completion of the CRMP, proposed projects and new decisions (e.g., issuance of a special-use permit) on federal lands are evaluated by the wild and scenic river-administering agency to ensure they protect and, to the extent possible, enhance river values (free-flowing condition, water quality and outstandingly remarkable values). The necessary evaluation framework is a detailed description of the existing conditions of these values at the time of designation. Absent this information it may not be possible to evaluate the effects of an activity relative to the non-degradation and...

Most rivers have flexible boundaries to accommodate specific features and river values. (Refer to Establishment of Wild and Scenic River Boundaries (1998).)