The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

The river-administering agency must take the actions necessary to remedy adverse impacts and/or show measurable progress in addressing identified adverse effects. The Wild & Scenic Rivers Act gives river-administering agencies authority to adjust or eliminate livestock grazing, or any other commercial use, if doing so is necessary to meet the protection and enhancement standard.

Rivers included in the National Wild & Scenic Rivers System by act of Congress (under Section 3(a) of the Wild & Scenic Rivers Act) are administered by one of four federal agencies: Bureau of Land Management (BLM), National Park Service (NPS), U.S. Forest Service (USFS), and/or U.S. Fish & Wildlife Service (FWS) as specified in the legislation. Rivers included in the National Wild & Scenic Rivers System at the request of a governor and designated by the Secretary of the Interior (under Section 2(a)(ii) of the Wild & Scenic Rivers Act) are administered by the respective...

Section 6(c) of the Wild & Scenic Rivers Act states:

. . . the appropriate Secretary shall issue guidelines, specifying standards for local zoning ordinances, which are consistent with the purposes of this Act. The standards specified in such guidelines shall have the object of (a) prohibiting new commercial or industrial uses other than commercial or industrial uses which are consistent with the purposes of this Act, and (b) the protection of the bank lands by means of acreage, frontage, and setback requirements on development.

The Wild...

Section 4(a) of the Wild & Scenic Rivers Act and the Interagency Guidelines describe and discuss content requirements, specific topics to be addressed, and the way in which information should be presented in such a study report. The National Environmental Policy Act (NEPA) process can, and is, readily merged with the requirements of the wild and scenic river study report. A wild and scenic river study report resulting from a decision in a land management plan usually summarizes and incorporates relevant information from the plan and associated NEPA document. For example, the location...

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

It is important to develop and apply standardized criteria through a documented evaluation process that may include a screening for potential wild and scenic rivers. If there doubt, evaluate the river according to the criteria in the Wild & Scenic Rivers Act, i.e., free-flowing condition and outstandingly remarkable values.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

Timber management activities on federal lands outside the corridor are managed to protect and enhance the values that caused the river to be designated. Measures needed to protect and enhance the river’s values are developed through the river planning process and include management direction as necessary for lands adjacent to the corridor.

Yes.  For purposes of eligibility evaluation, the volume of flow is sufficient if it is enough to sustain or complement the outstandingly remarkable values identified within the segment.  Rivers with intermittent or non-perennial flows exist within the National Wild & Scenic Rivers System and may be representative of rivers within particular physiographic regions.

No. The protection afforded by Section 7(b) of the Wild & Scenic Rivers Act does not apply to Section 5(d)(1) study rivers. However, the managing agency should, within its authorities, protect the values which make the river eligible or suitable (free-flowing condition, water quality and outstandingly remarkable values).

Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical report of the Interagency Wild and Scenic Rivers...

Once such a river segment has been found to be ineligible, the agency will describe the basis for this finding in the study report and follow its internal procedures to transmit the report to the Congress in accordance with Section 7(b) of the Wild & Scenic Rivers Act.

No. The Wild & Scenic Rivers Act does not limit the amount of land that may be acquired through purchase of easements, i.e., acquisition of partial rights, such as development rights.

Under Section 5(a), Congress directs that a study be conducted on identified river segments (usually within three years).  The designated federal agency conducts a study and subsequently reports its findings through the appropriate Secretary.  As a general rule, where joint agency jurisdictions are involved, the cooperating agencies coordinate their efforts prior to making recommendations or submitting reports.

Under Section 5(d)(1), federal agencies are directed to identify and evaluate potential additions to the National Wild & Scenic Rivers System through agency...

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

Differences include, but are not limited to, the following areas:

  1. Motorized boats and other motors may be allowed in wild and scenic rivers classified as wild, whereas the administering Secretary has the discretion to continue the use of motorized boats and airplane landings in wilderness where such uses are traditionally established. In areas that are both a wild and scenic river and wilderness, the most restrictive provisions of the two acts apply, subject to any area-specific legislative language.

  2. New dams are prohibited in wild and scenic rivers. The...

Yes, the federal government may seek to control use on adjacent lands under very limited circumstances. The Constitution gives the federal government certain limited powers to control uses on state-owned lands that affect adjacent federal property. These powers may be exercised through the Property Clause, which provides that, “Congress shall have the power to make all needful rules and regulations respecting the territory or the property belonging to the United States.”

The federal government may also regulate use and/or activities occurring on the surface waters...

Some examples of other similar outstandingly remarkable values include botanical, hydrological, paleontological, scientific, or heritage values.

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Congress declared its intent to protect the water quality of rivers added to the National Wild & Scenic Rivers System in Section 1(b) of the Wild & Scenic Rivers Act. Congress further specified that the river-administering agencies cooperate with the EPA and state water pollution control agencies to eliminate or diminish water pollution (Section 12(c)).

Corridors may not exceed an average of 320 acres per river mile over the designated portion of the river (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). Agencies delineate boundaries based on natural or manmade features (canyon rims, roads and ridge tops, etc.) and legally identifiable property lines.

The federal wild and scenic river-administering agency is responsible for implementing the Wild & Scenic Rivers Act’s requirements, including the development of a comprehensive management plan for each river within three full fiscal years from the date of designation. It is also responsible to protect and enhance a river’s values, through its authorities on federal lands and through voluntary, cooperative strategies developed with other governments, tribal nations, and landowners on non-federal lands, and to evaluate water resources projects under Section 7(a).

Yes. Water may be secured through a variety of protection strategies, in the interim. Ultimately, the United States should secure a federal reserved water right in state court or the appropriate forum. Interim measures may include, but are not limited to: state instream flow programs, reservoir operation schedules, endangered species flow recommendations, conservation techniques, cooperative agreements, and water right purchases from willing sellers.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water...

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

Section 16(b) of the Act defines free-flowing as “existing or flowing in a natural condition without impoundment, diversion, straightening, rip-rapping, or other modification of the waterway. The existence, however, of low dams, diversion works and other minor structures at the time any river is proposed for inclusion in the national wild and scenic rivers system shall not automatically bar its consideration for such inclusion: Provided, that this shall not be construed to authorize, intend, or encourage future construction of such structures in components of the national wild and...

There are two ways rivers are designated in the National Wild & Scenic Rivers System:

  • By Act of Congress
    This requires legislation to amend Section 3(a) of the Act.  Rivers designated by Congress are listed in Section 3(a) of the Act.
  • By the Secretary of the Interior
    This requires...

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

The Act (Public Law 90-542; 16 U.S.C. 1271-1287) was signed on October 2, 1968. It has been amended many times, primarily to designate additional rivers and authorize additional rivers for study for possible inclusion.

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...

Any federally assisted construction project—by loan, grant, permit, license, or otherwise—which would affect the free-flowing condition of a wild and scenic river. This includes any hydroelectric project licensed by the Federal Energy Regulatory Commission (FERC)  under Part 1 of the Federal Power Act (36 CFR 297).


Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical...

Yes. Section 7(b) of the Wild & Scenic Rivers Act provides the same protection to study rivers authorized by Congress, except that the qualifying word “unreasonably” does not appear before “diminish” for projects located above, below, or on a stream tributary to the study segment’s boundaries. The intent and effect is to provide greater protection for study rivers from proposed hydroelectric facilities or other federally assisted water resource projects during the time-limited study process. Identical protection from water resource projects also applies to rivers that were previously...

No. The United States determines the quantity necessary to protect flow-dependent outstandingly remarkable values.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Yes. To withdraw a scenic or recreational river segment, the managing agency must submit a separate public land order or notice of realty action.

Timber management activities on federal lands within wild and scenic river corridors must be designed to help achieve land-management objectives consistent with the protection and enhancement of the values that caused the river to be added to the National Wild & Scenic Rivers System. Management direction needed to protect and enhance the river’s values is developed through the river planning process. Wild and scenic river designation is not likely to significantly affect timber management activities beyond existing measures to protect riparian zones, wetlands, and other resource values...

Subject to valid existing rights, rivers authorized for study under Section 5(a) of the Wild & Scenic Rivers Act are withdrawn under the mining laws while in study status; this withdrawal covers the bed and bank and federal lands situated within one-quarter mile of the bank on each side of the river. River study areas are not withdrawn from mineral leasing but are subject to conditions determined by the appropriate Secretary necessary to safeguard the area during the study period. However, the bed and bank and federal lands within two miles of the bank of each side of the rivers...

A river identified for study under Section 5(d)(1) is protected by each agency’s policy; i.e., the Wild & Scenic Rivers Act provides no statutory protections. To the extent of each agency’s authority, the river’s free-flowing condition, water quality, outstandingly remarkable values, and classification are protected. Prior to a suitability study, the inventoried classification is protected. If, as the result of a suitability study, a less restrictive classification is recommended for a river or portion thereof, the agency is obligated to protect this recommended classification.

Prior to 1986, Section 3(b) of the Wild & Scenic Rivers Act required the river-administering agency to “prepare a plan for necessary developments in connection with its administration in accordance with such classification.” Through a generic amendment of the Wild & Scenic Rivers Act in 1986, Section 3 was amended with a new subsection requiring a “comprehensive management plan . . . to provide for protection of the river values” (Section 3(d)(1)). The comprehensive river management plan (CRMP) must address:

  1. Resource protection;

  2. Development of lands...

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

Yes. Under Section 5(a) of the Wild & Scenic Rivers Act, the public is involved in the study of rivers authorized by Congress. The report associated with a congressionally authorized study addresses subjects such as current status of land ownership and use in the area; reasonably foreseeable potential uses of land and water which would be affected by designation; the federal agency to administer the river if designated; and the ability of, and estimated costs to, state and local agencies to participate in the administration of such rivers. The public and state, local and tribal...

The need to amend a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed amendment associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP) as a basis to make a recommendation to Congress to amend the Wild & Scenic Rivers Act.

The river-administering agency can only recommend such a change to Congress. A subsequent...

Federal lands within the boundaries of designated river areas (one-quarter mile—one-half mile for rivers in Alaska located outside national parks—from the bank on each side of the river) classified as wild are withdrawn from appropriation under the mining and mineral leasing laws by Sections 9(a) and 15(2) of the Wild & Scenic Rivers Act. Federal lands within the boundaries of designated river areas classified as scenic or recreational are not withdrawn under the Wild & Scenic Rivers Act from the mining and mineral leasing laws....

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

A variety of methodologies are used to determine instream flows necessary to protect flow-dependent outstandingly remarkable values for a specific wild and scenic river. Methodologies can range from staff/expert opinions (e.g., flows necessary for boating) to complicated hydraulic models (e.g., Instream Flow Incremental Methodology and Physical Habitat Simulation Models) used to simulate fish habitat requirements.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager...

Yes. The “equal footing” principle of the Constitution and the Submerged Lands Act of 1953 afford each state the ownership of lands and natural resources under navigable rivers. These submerged lands generally extend from bank-to-bank or to the mean or ordinary high water mark.

River segments may be tentatively classified for protective management purposes prior to a final suitability determination and/or congressional action.  This ensures that river values and characteristics are protected (subject to agency policies and standards) until the evaluation process and possible designation is completed.