The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

Section 6(c) of the Wild & Scenic Rivers Act states:

. . . the appropriate Secretary shall issue guidelines, specifying standards for local zoning ordinances, which are consistent with the purposes of this Act. The standards specified in such guidelines shall have the object of (a) prohibiting new commercial or industrial uses other than commercial or industrial uses which are consistent with the purposes of this Act, and (b) the protection of the bank lands by means of acreage, frontage, and setback requirements on development.

The Wild...

Section 16(b) of the Act defines free-flowing as “existing or flowing in a natural condition without impoundment, diversion, straightening, rip-rapping, or other modification of the waterway. The existence, however, of low dams, diversion works and other minor structures at the time any river is proposed for inclusion in the national wild and scenic rivers system shall not automatically bar its consideration for such inclusion: Provided, that this shall not be construed to authorize, intend, or encourage future construction of such structures in components of the national wild and...

Section 6(a)(1) of the Wild & Scenic Rivers Act states:

The Secretary of the Interior and the Secretary of Agriculture are each authorized to acquire lands and interests in land within the authorized boundaries of any component of the national wild and scenic rivers system designated in Section 3 of this act . . . but he shall not acquire fee title to an average of more than 100 acres per mile on both sides of the rivers.

The Wild & Scenic Rivers Act authorizes fee title acquisition to the equivalent of about a 400 foot wide strip of land...

The federal government has rarely exercised its eminent domain powers with respect to wild and scenic rivers. Of the 226 rivers in the National Wild & Scenic Rivers System as of June 2022, condemnation for fee title has been used on only four rivers. Nearly all of the federal government’s use of condemnation occurred in the early years of the Wild & Scenic Rivers Act’s implementation when the attitudinal climate was one of federal acquisition. Similarly, the use of scenic easement condemnation has also been used very rarely, and then only on seven rivers, all designated prior to...

It depends on whether the collecting activity is commercial or noncommercial in nature and subject to river-administering agency regulation. Mining under the 1872 mining law is a commercial and business activity tied to valid existing rights of claims and is regulated as such (36 CFR 228, 43 CFR 3809, 8365, et al).

Non-commercial mineral collecting for recreational purposes (e.g., hobby collecting, rock-hounding, gold panning, sluicing, or dredging) may be authorized by the Bureau of Land Management or the U.S. Forest Service depending on the amounts collected, size and scale of...

Amending the lateral boundary of a designated river requires analysis and decision under the National Environmental Policy Act (NEPA). The environmental analysis process need not be complicated and may only require the proposed action and a no-action alternative. Amendment of a wild and scenic river boundary may also be timed with revision of the comprehensive river management plan and related decision under the NEPA. In either case, notice of the amended boundary should be published in the Federal Register and the legal description and maps forwarded to Congress and made...

Agency officials are required to coordinate when their responsibilities relevant to wild and scenic rivers overlap.  Officials should determine the level of study to be conducted, who will lead the study, and, to the extent necessary and feasible, prepare a joint document for submission to Congress or congressional delegations.

Yes, a CRMP is developed in compliance with the NEPA. The purpose and need for the proposed action is to protect and enhance the values for which the river was designated (free-flowing condition, water quality, and outstandingly remarkable values), within its classification(s). The proposed action establishes appropriate goals, objectives, and/or desired conditions to meet those purposes. Alternative courses of actions are developed and analyzed relative to achieving overall goals and desired conditions within the wild and scenic river corridor. A “no action” alternative, representing the...

The Act (Public Law 90-542; 16 U.S.C. 1271-1287) was signed on October 2, 1968. It has been amended many times, primarily to designate additional rivers and authorize additional rivers for study for possible inclusion.

Wild and scenic rivers may qualify as a Section 4(f) property, but designation of a river under the Wild & Scenic Rivers Act does not invoke Section 4(f) in the absence of significant Section 4(f) attributes and qualities. The Federal Highway Administration (FHWA), in consultation with the river-administering agency, determines on a case-by-case basis whether Section 4(f) applies. For example, Section 4(f) may apply to reaches of designated wild and scenic rivers that are publicly owned, open to the public and include recreation as a primary purpose, feature, attribute, or value....

Upon congressional authorization for a study (Section 5(a)) or by federal agency initiative (Section 5(d)(1)).

Yes. River-administering agencies have an affirmative duty to evaluate pre-existing uses on federal lands to determine whether such uses are protecting the values for which the wild and scenic river was designated. Grazing may continue when consistent with protecting river values. If grazing practices are determined to be inconsistent with wild and scenic river management objectives, then changes in grazing practices may be required.

A range of projects are allowable to restore natural channel processes and habitat, including placement of limited rock and wood, native plantings to stabilize streambanks, and the removal or addition of fish barriers. Such projects are most likely to protect river values, including a river’s free-flowing condition, provided they: 

  1. Mimic the effects of naturally occurring events such as trees falling in and across the river (including the formation of wood jams), boulders tumbling in or moving down the river course, exposure of bedrock outcrops, bank sloughing or...

Yes, but with many restrictions. It is important to note that condemnation is a tool that has been used only rarely on wild and scenic rivers. The objective of wild and scenic river designation is to protect and, as possible, enhance the values which caused the river to be designated. Should some proposed or actual use clearly threaten the values the river was designated to protect, the river managing agency would work with a landowner to explore ways to avert the threat through local zoning, state provisions, land exchanges, or purchases on a willing-seller/willing-buyer basis....

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Differences include, but are not limited to, the following areas:

  1. Motorized boats and other motors may be allowed in wild and scenic rivers classified as wild, whereas the administering Secretary has the discretion to continue the use of motorized boats and airplane landings in wilderness where such uses are traditionally established. In areas that are both a wild and scenic river and wilderness, the most restrictive provisions of the two acts apply, subject to any area-specific legislative language.

  2. New dams are prohibited in wild and scenic rivers. The...

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

The river-administering agency must take the actions necessary to remedy adverse impacts and/or show measurable progress in addressing identified adverse effects. The Wild & Scenic Rivers Act gives river-administering agencies authority to adjust or eliminate livestock grazing, or any other commercial use, if doing so is necessary to meet the protection and enhancement standard.

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

The federal wild and scenic river-administering agency is responsible for implementing the Wild & Scenic Rivers Act’s requirements, including the development of a comprehensive management plan for each river within three full fiscal years from the date of designation. It is also responsible to protect and enhance a river’s values, through its authorities on federal lands and through voluntary, cooperative strategies developed with other governments, tribal nations, and landowners on non-federal lands, and to evaluate water resources projects under Section 7(a).

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

These facilities will be provided if they are consistent with the management plan for each river and if funds are available.

Corridors may not exceed an average of 320 acres per river mile over the designated portion of the river (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). Agencies delineate boundaries based on natural or manmade features (canyon rims, roads and ridge tops, etc.) and legally identifiable property lines.

The need to amend a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed amendment associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP) as a basis to make a recommendation to Congress to amend the Wild & Scenic Rivers Act.

The river-administering agency can only recommend such a change to Congress. A subsequent...

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

Yes. Section 7(b) of the Wild & Scenic Rivers Act provides the same protection to study rivers authorized by Congress, except that the qualifying word “unreasonably” does not appear before “diminish” for projects located above, below, or on a stream tributary to the study segment’s boundaries. The intent and effect is to provide greater protection for study rivers from proposed hydroelectric facilities or other federally assisted water resource projects during the time-limited study process. Identical protection from water resource projects also applies to rivers that were previously...

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under the Wild & Scenic Rivers Act and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

Generally, no. Restrictions on public boating access and the implementation of entry permit systems (rationing and/or allocation) are not usually related to designation. Limitations on boating usually relate to the amount of use and/or types of user. Those rivers with use levels or types of use beyond acceptable limits (i.e., resulting in impacts to the values) may necessitate restricted access regardless of designation.

The need to clarify the terminus should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the terminus to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the dam” included a dam and dam-...

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

Examples include, but are not limited to, bank stabilization/revetments; bridges (e.g., abutments, piers, approaches); emergency repairs; channelization; channel restoration; culverts; dams and dam removal; dredging or excavation; fish habitat/passage restoration or enhancement; gravel mining; in-channel transmission towers; levees; pipelines; recreation facilities such as boat ramps and fishing piers; water diversions/wells; and activities that are authorized under Section 404 of the Clean Water Act by the United States Army Corps of Engineers (ACOE).


Review of...

No, not unless necessary to protect public safety, the river’s water quality, or other resource values. Recreational use of our nation’s rivers is increasing in both magnitude and extent, i.e., the types of recreational activities pursued and the technologies being used. Whether and how to restrict recreational use is a key issue in the planning process, which includes extensive local, regional, and national public involvement.

Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

No. Federal agencies do not have the authority to reimburse landowners for damage to their lands as a result of public use. However, wild and scenic river designation is unlikely to increase or invite vandalism. Granting access remains the owner’s responsibility and vandalism is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

No. The protection afforded by Section 7(b) of the Wild & Scenic Rivers Act does not apply to Section 5(d)(1) study rivers. However, the managing agency should, within its authorities, protect the values which make the river eligible or suitable (free-flowing condition, water quality and outstandingly remarkable values).

Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical report of the Interagency Wild and Scenic Rivers...

Generally, existing agricultural and grazing practices, and related structures are not affected by designation. The Wild & Scenic Rivers Act does not give federal agencies authority to regulate private land. Consequently, the only effect of designation is to authorize the purchase of easements within the river corridor, and to enable federal agency staff to provide technical assistance to private landowners interested in reducing impacts on the river’s water quality and riparian integrity.

Projects with the following attributes are generally considered most harmonious with river ecosystems:

  • Those made of native materials, e.g., wood, rock, vegetation, and so forth that are similar in type, composition or species to those in the vicinity of the project.
  • Those using construction materials that are natural in appearance, e.g., logs with bark intact as opposed to being peeled and whole naturally weathered rocks as opposed to split or fractured (i.e., riprap).
  • Those with materials placed in locations, positions, and quantities mimicking natural...

Some examples of other similar outstandingly remarkable values include botanical, hydrological, paleontological, scientific, or heritage values.

Yes. Under Section 5(a) of the Wild & Scenic Rivers Act, the public is involved in the study of rivers authorized by Congress. The report associated with a congressionally authorized study addresses subjects such as current status of land ownership and use in the area; reasonably foreseeable potential uses of land and water which would be affected by designation; the federal agency to administer the river if designated; and the ability of, and estimated costs to, state and local agencies to participate in the administration of such rivers. The public and state, local and tribal...

Ideally one coordinated CRMP is developed with each wild and scenic river-administering agency documenting its respective decisions. In a few cases, separate plans may be required. However, even in this case, the planning process is conducted jointly to the greatest extent possible to ensure consistency of outstandingly remarkable values, classification, standards, and monitoring.

There are no known studies comparing river use levels before and after wild and scenic river designation with changes in use levels of similar non-wild and scenic rivers. Factors other than wild and scenic river designation (i.e., river and water attributes, access to the river, and availability of facilities and commercial services) are considered to be the major influences on river use levels. For wild and scenic rivers, as for other rivers managed by federal agencies, the implementation of permit systems or other limits of use are typically undertaken when use exceeds an acceptable...

Any federally assisted construction project—by loan, grant, permit, license, or otherwise—which would affect the free-flowing condition of a wild and scenic river. This includes any hydroelectric project licensed by the Federal Energy Regulatory Commission (FERC)  under Part 1 of the Federal Power Act (36 CFR 297).


Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical...

To be eligible for designation, a river must be free-flowing and contain at least one "outstandingly remarkable value," i.e., scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar value.

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.