The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

No. The designation does not supersede existing, valid water rights.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Designation may cause an increase in use along the river as new visitors seek it out. However, the wild and scenic river management requirements should ensure that any such increase will not damage resources on private property. If anything, there will be increased oversight after designation, discouraging littering, trespass and vandalism. Private landowners may continue to post their property with “No Trespassing” signs or require users to obtain landowner permission.

Yes. The Wild & Scenic Rivers Act anticipates the need for occasional adjustment of the lateral (river corridor) boundary, directing that such amendment follow the same process as described for the initial boundary development in Sections 3(b) and (c) of the Wild & Scenic Rivers Act. The legally established river corridor might require amendment to better reflect protection of outstandingly remarkable values or as the result of identification of a new outstandingly remarkable value.

No. The Wild & Scenic Rivers Act does not limit the amount of land that may be acquired through purchase of easements, i.e., acquisition of partial rights, such as development rights.

No, not unless necessary to protect public safety, the river’s water quality, or other resource values. Recreational use of our nation’s rivers is increasing in both magnitude and extent, i.e., the types of recreational activities pursued and the technologies being used. Whether and how to restrict recreational use is a key issue in the planning process, which includes extensive local, regional, and national public involvement.

In agency parlance used for planning purposes, river “areas” include the entire length of a study or designated river and its adjacent lands, an average of 320 acres per river mile (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). A river “segment” is a portion of the river area which has been delineated for evaluation and planning purposes. Its subsequent classification is dependent upon the level of development of the shoreline, watercourse and access at the time of designation. Significantly different...

Generally, existing livestock grazing practices and related structures are not affected by designation. The Interagency Guidelines state that agricultural practices should be similar in nature and intensity to those present in the area at the time of designation, and that grazing may be compatible with all river classifications (wild, scenic or recreational). Grazing and other public uses may occur in a wild and scenic river corridor as long as the uses do not adversely impact or otherwise degrade the values for which a river was designated.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

Yes. The “equal footing” principle of the Constitution and the Submerged Lands Act of 1953 afford each state the ownership of lands and natural resources under navigable rivers. These submerged lands generally extend from bank-to-bank or to the mean or ordinary high water mark.

Section 6(c) of the Wild & Scenic Rivers Act states:

. . . the appropriate Secretary shall issue guidelines, specifying standards for local zoning ordinances, which are consistent with the purposes of this Act. The standards specified in such guidelines shall have the object of (a) prohibiting new commercial or industrial uses other than commercial or industrial uses which are consistent with the purposes of this Act, and (b) the protection of the bank lands by means of acreage, frontage, and setback requirements on development.

The Wild...

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...

The study report for a congressionally authorized Section 5(a) study river is required to be forwarded by the study agency within the period specified in Section 5(b). This study report must be forwarded to Congress no matter what the outcome of the study.

Unlike the firm deadlines established for Section 5(a) study reports, the Act is silent in regard to Section 5(d)(1) rivers. Thus the river-administering agencies have considerable latitude in how and when to transmit the study report for rivers they have found suitable and are recommending to Congress for designation. The...

Yes. The Wild & Scenic Rivers Act directs other federal agencies to protect river values. It explicitly recognizes the regulatory roles of the Federal Energy Regulatory Commission and the Environmental Protection Agency in protecting wild and scenic rivers, and directs other federal departments and agencies that permit or assist in the construction of water resources projects to do likewise. The role of such federal agencies in water resources project construction may be through regulation, direct funding, or indirectly funding by providing federal assistance to others.

All...

A variety of methodologies are used to determine instream flows necessary to protect flow-dependent outstandingly remarkable values for a specific wild and scenic river. Methodologies can range from staff/expert opinions (e.g., flows necessary for boating) to complicated hydraulic models (e.g., Instream Flow Incremental Methodology and Physical Habitat Simulation Models) used to simulate fish habitat requirements.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager...

The following summarizes the sections of the Wild & Scenic Rivers Act related to water resources (quality and quantity):

Section 1(b) of the Wild & Scenic Rivers Act establishes that the national policy of dam and other construction be complemented by a policy that would preserve other selected rivers or sections thereof “in their free-flowing condition to protect the water quality of such rivers and to fulfill other vital national conservation purposes.”

Section 10(a) states: “Each component of the national wild and scenic rivers system shall be administered in...

In many cases, there may be no practical effect. However, laws like the Wilderness Act do allow certain activities in designated wilderness which may be incompatible on a wild and scenic river, e.g., water resource developments if authorized by the President. In addition, wild and scenic river designation prohibits federal participation in, or assistance to, water resource developments upstream or downstream of a designated river (potentially outside the wilderness area) which may adversely affect the designated river segment. Agencies are required by policy and law to evaluate potential...

Wild and scenic river study reports are prepared in three instances:

  1. When Congress authorizes a study pursuant to Section 5(a) of the Wild & Scenic Rivers Act.

  2. For eligible rivers that have also been determined suitable by a federal land management agency pursuant to Section 5(d)(1) of the Wild & Scenic Rivers Act, when the agency deems it appropriate to forward the recommendation.

  3. For state-nominated Section 2(a)(ii) rivers, the National Park Service prepares a report determining whether the candidate river meets the requirements of...

The Wild & Scenic Rivers Act requires that detailed boundaries portrayed on maps be established and submitted to Congress within one year of designation. Agencies may finalize boundaries through their respective land management planning process.

Pending the establishment of detailed river boundaries, the Wild & Scenic Rivers Act specifies that the interim boundary is one-quarter mile on each side of the river as measured from the ordinary high water mark.

Section 3(b) of the Wild & Scenic Rivers Act states:

The agency charged with the...

Yes, but with many restrictions. It is important to note that condemnation is a tool that has been used only rarely on wild and scenic rivers. The objective of wild and scenic river designation is to protect and, as possible, enhance the values which caused the river to be designated. Should some proposed or actual use clearly threaten the values the river was designated to protect, the river managing agency would work with a landowner to explore ways to avert the threat through local zoning, state provisions, land exchanges, or purchases on a willing-seller/willing-buyer basis....

No. The United States determines the quantity necessary to protect flow-dependent outstandingly remarkable values.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

Yes. Under Section 5(a) of the Wild & Scenic Rivers Act, the public is involved in the study of rivers authorized by Congress. The report associated with a congressionally authorized study addresses subjects such as current status of land ownership and use in the area; reasonably foreseeable potential uses of land and water which would be affected by designation; the federal agency to administer the river if designated; and the ability of, and estimated costs to, state and local agencies to participate in the administration of such rivers. The public and state, local and tribal...

Wild and scenic river designations generally cause property values to remain stable or increase. For example, see Economic Benefits of Conserved Rivers: An Annotated Bibliography (Porter, B., Collier, S., Becerra, N., and Schultz, J. 2001. National Park Service – Rivers and Trails Conservation and Assistance Program, Washington, DC. 27pp.).

No. Where tribal lands are involved, sovereign tribes retain authority over the lands; however, the river-administering agencies seek opportunities to collaborate in protecting values of joint concern.

No. Under the Wild & Scenic Rivers Act, the federal government has no authority to regulate or zone private lands. Land use controls on private lands are solely a matter of state and local zoning. Although the Wild & Scenic Rivers Act includes provisions encouraging the protection of river values through state and local governmental land use planning, there are no binding provisions on local governments. In the absence of state or local river protection provisions, the federal government may seek to protect values by providing technical assistance, entering into agreements with...

The Act (Public Law 90-542; 16 U.S.C. 1271-1287) was signed on October 2, 1968. It has been amended many times, primarily to designate additional rivers and authorize additional rivers for study for possible inclusion.

It depends on whether the collecting activity is commercial or noncommercial in nature and subject to river-administering agency regulation. Mining under the 1872 mining law is a commercial and business activity tied to valid existing rights of claims and is regulated as such (36 CFR 228, 43 CFR 3809, 8365, et al).

Non-commercial mineral collecting for recreational purposes (e.g., hobby collecting, rock-hounding, gold panning, sluicing, or dredging) may be authorized by the Bureau of Land Management or the U.S. Forest Service depending on the amounts collected, size and scale of...

The Wild & Scenic Rivers Act does not specifically mention aquatic or upland non-indigenous species. While non-indigenous species may be introduced—provided that doing so is not contrary to another law or the policy of the managing agency, and would not result in the degradation to the river’s values—the use of native species is generally preferred. Indirect impacts of introducing non-indigenous species, e.g., increasing recreational fishing, should also be considered. Additional guidance for a specific river is usually included in its management plan.

Local government entities are encouraged by federal wild and scenic river-administering agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures. Their participation in development of the comprehensive river management plan (CRMP) in areas of mixed ownership is essential to ensure an enduring planning strategy that protects river values and respects the rights of landowners. In some cases, local governments have chosen to strengthen land-use requirements during a wild and scenic river study, in...

These facilities will be provided if they are consistent with the management plan for each river and if funds are available.

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

Rivers included in the National Wild & Scenic Rivers System by act of Congress (under Section 3(a) of the Wild & Scenic Rivers Act) are administered by one of four federal agencies: Bureau of Land Management (BLM), National Park Service (NPS), U.S. Forest Service (USFS), and/or U.S. Fish & Wildlife Service (FWS) as specified in the legislation. Rivers included in the National Wild & Scenic Rivers System at the request of a governor and designated by the Secretary of the Interior (under Section 2(a)(ii) of the Wild & Scenic Rivers Act) are administered by the respective...

Section 16(c) of the Wild & Scenic Rivers Act defines a scenic easement as follows:

“Scenic easement” means the right to control the use of land (including the air space above such land) within the authorized boundaries of a component of the wild and scenic river system, for the purpose of protecting the natural qualities of a designated wild, scenic, or recreational river area, but such control shall not affect, without the owner’s consent, any regular use exercised prior to the acquisition of the easement.

While the Wild & Scenic Rivers...

Rivers designated under Section 3(a) of the Wild & Scenic Rivers Act, and most designated under Section 2(a)(ii), are classified in one of three categories depending on the extent of development and accessibility along each section. Designated river segments are classified and administered under one of the following, as defined in Section 2(b) of the Wild & Scenic Rivers Act:

...

A primary objective of wild and scenic river designation is to protect and enhance riparian area function and other river-related natural values. Specific actions to meet the objective are typically set forth in the management plan required for each river.

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

Yes. Regardless of whether a river is designated as a wild and scenic river, states have special responsibilities and management constraints with respect to state-owned lands underlying navigable waters. These special responsibilities arise from the Public Trust Doctrine, which requires states to exercise regulatory authority over navigable riverbeds to ensure that the paramount right of public use of the rivers and riverbeds for navigation, commerce, recreation, and related purposes is not substantially impaired. As a matter of common law, the states hold lands...

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

When Congress proposes a bill to designate an eligible river for which a suitability study has not been completed, the potential river-administering agency should endeavor to:

  1. Describe the resource and social factors typically evaluated in a study;
  2. Identify potential issues; and
  3. Assess its ability to manage the recommended component as a wild and scenic river.

This information provides the basis for the Administration’s decision to support or oppose the proposed designation.

No. The river study, enabling legislation, and subsequent management planning process will consider how best to protect river values while recognizing private property rights.

Once determined eligible, river segments are tentatively classified for study as either wild, scenic, or recreational based on the level of development of the shoreline, watercourse and access at the time of river is found eligible. If designated by Congress, the river’s enabling legislation generally specifies the classification.

Generally, no. Restrictions on public boating access and the implementation of entry permit systems (rationing and/or allocation) are not usually related to designation. Limitations on boating usually relate to the amount of use and/or types of user. Those rivers with use levels or types of use beyond acceptable limits (i.e., resulting in impacts to the values) may necessitate restricted access regardless of designation.

No. The protection afforded by Section 7(b) of the Wild & Scenic Rivers Act does not apply to Section 5(d)(1) study rivers. However, the managing agency should, within its authorities, protect the values which make the river eligible or suitable (free-flowing condition, water quality and outstandingly remarkable values).

Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical report of the Interagency Wild and Scenic Rivers...

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

Timber management activities on federal lands outside the corridor are managed to protect and enhance the values that caused the river to be designated. Measures needed to protect and enhance the river’s values are developed through the river planning process and include management direction as necessary for lands adjacent to the corridor.

Timber management activities on non-federal lands outside the corridor are guided by state and local authorities. The river manager may provide technical assistance and/or work with state/local governments to protect river values.

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

Yes.  There are three classifications (wild, scenic and recreational) that may be applied to a particular river segment. Distinct segments along the designated reach may contain differing and non-overlapping classifications (wild, scenic, or recreational), e.g., a 100-mile wild and scenic river may be classified as wild for 50 miles, scenic for 30 miles, and recreational for 20 miles.